By Sabrina Artusa

At the Sterling Woods Condominium annual meeting on Feb. 20, New Leaf Energy Senior Director of Business Development Michael Conway spoke to the residents, whose condominiums neighbor the proposed site at 1575 Route 25A in Port Jefferson Station. 

This proposal comes after the Town of Brookhaven rejected a rezoning application by New Leaf Energy in June 2024. 

Now, New Leaf Energy, a renewable energy developer, is planning an 8.75-megawatt battery energy storage system in an area with the appropriate light industrial zoning. The system would occupy 22,142 square feet and can power 8,500 single-family homes for 4 hours. 

Conway, joined by Energy Safety Response Group co-founder Paul Rogers, reviewed the site plan, which neighbors a gas station. The property will be encompassed by a 10-foot-tall fence and vegetative screening and will include a 50-ft setback. 

“Dense places are the most difficult places to get electricity to,” Conway said, addressing the location. “We need to have electricity whether it comes through a fossil plant, or it comes in through a solar plant, or it comes in through transmission lines. Energy storage systems are an efficient way to deliver more electricity to an area without building more poles and wires all over the place and more power plants.”

One resident said, “I don’t think we disagree with technology. I don’t think anyone does. We have to look forward. But where are you putting it? There is no benefit to be putting this here, absolutely none. Basically, you want us to be a test case for your business.” 

New Leaf Energy will be working with manufacturers to develop the system and will then sell the BESS. Defined as a business that “establishes important partnerships with landowners, utilities and local communities to brainstorm, secure, design and permit community and utility-scale renewable energy,” New Leaf Energy essentially works to give the project momentum and get it approved before then selling to another company for around $3 million to $4 million.  

“Our business model is to transfer ownership to a long-term asset owner just prior to construction,” Conway said. It usually takes 6-8 months to find a buyer. The buyer will then be responsible for the safety and operation of the system, including the battery monitoring system. 

The oldest BESS New Leaf Energy has created was built in 2018. The largest is 200 megawatts. 

This system will help manage the grid during peak hours and potentially save PSEG from having to purchase additional equipment. The BESS will be privately owned so will not, in theory, be the direct cause of rate increases from PSEG. Instead, the system will store energy in times of low demand and sell it back during high-demand times. 

Rogers, who has been a prominent figure in the battery energy storage conversation throughout Brookhaven, says that manufacturers are required to permit large-scale controlled failures on their equipment. This could mean burning cells or, in some cases, modules. 

Rogers said that thermal runaway is caused when the cells are interfered with or abused and are unable to regulate normally, thus causing the liquid within the cells to turn to gas. For instance, if a container is not sealed properly when it is raining, the water could cause electrical problems. 

Rogers, who has helped implement and navigate the various safety codes, said that the BESS has to be listed under Underwriters Laboratories UL9540, which authorizes that the equipment is up to standard, and must adhere to precautions listed in the National Fire Protection Association codebook as well as New York State codes. 

The Moss Landing fire, which burned for days and led to the evacuation of residents, was described by Brookhaven Councilman Jonathan Kornreich (D, Stony Brook) as “sobering.” The old and outdated system consisted of nickel manganese cobalt batteries as opposed to lithium iron phosphate, which is less energy dense, and was situated in a designated-use building.

Rogers said of the 750-megawatt system, “we would never use that technology today.” 

“This is fairly new technology,” said Kornreich. “It is almost as if the car had been invented and they said oh this is a great way to make deliveries and drive around town but they haven’t invented the brake pedal yet…we don’t know yet and that is why we have to go slow with these things.”

(Left to right) William Miller, Nicholas Petrakis, James McDaniel, and Thom Rainwater looking at their prepared presentation. Photo by Sabrina Artusa

By Sabrina Artusa

Savion Energy representatives stood before the Three Village Civic Association membership Monday, Nov. 4, to present their proposed battery storage facilities in East Setauket. Savion is a Shell Group portfolio company that develops utility-scale solar and energy storage projects. 

One project is proposed for a lot off Sheep Pasture Road, while another location would be between Parsonage Road and Old Town Road. 

Environmental benefits 

These proposals arrive in the midst of a statewide effort to increase green energy sources and transition away from fossil fuels. In 2022, Gov. Kathy Hochul (D) doubled the state’s energy storage goal. Further, the Climate Leadership and Community Protection Act, signed by Gov. Andrew Cuomo (D) in 2019, aims for 100% zero-emission electricity by 2040. 

These battery storage facilities is one among many being proposed across Long Island as power plants like the fossil-burning plant in Port Jefferson close. 

Savion’s facilities will consist of containers of lithium-ion batteries that store excess energy during peak hours and discharge electricity as needed. The batteries, which have a life of about 20 years, will be charged and discharged on a daily basis but would be especially useful during increment weather when renewable energy sources are unreliable. 

The batteries would take eight hours to charge and allow Long Island to ease its reliance on nonrenewable energy. The transition is intended to diminish adverse environmental effects by lessening greenhouse gas emissions. 

Location and safety 

The location is one of the major topics of contention. The locations are in close proximity to neighborhoods, making some residents uneasy.

Nicholas Petrakis, senior consultant of consulting firm Energy Safety Response Group, assured civic association members that scrupulous measures were instituted to minimize the chances of thermal runaway. This process occurs when a damaged cell releases heat and gasses, thus triggering the same reaction in nearby cells. 

James McDaniel, senior battery storage engineer at Savion, said their systems are containerized and “designed to burn themselves out” and “fail safely”. The sites will be remotely monitored constantly by a team of experts, Petrakis said, and there is a sensor system that would notify the fire department and shut down the battery if anything is amiss.

Toxic off-gassing is a possibility — one that Petrakis said is a possible effect of most residential fires as well. Many present were apprehensive by this prospect. Further, the water used to counter any fires was a cause for concern, but Sean Flannery, senior director of permitting & environmental at Savion, said that “water runoff has not shown to be an issue” and that it will be contained on the property. 

Residents from across the Island were present at this meeting, hoping to learn more about the battery storage systems that are proposed in their own towns. Many questioned the location, asking why it was necessary to install the facilities in such a dense area. 

“Why would you consider putting something like this in this dense area?” one man asked. “The fact that in your proposed pictures you can see people’s houses doesn’t instill support.” 

Indeed, the buffer wall intended to keep the noise to the 50 decibels allowed in the Town of Brookhaven code is visible in a picture of what Savion expects each site to look like from a surrounding residential area. 

William Miller, managing partner at Clearview Consultants, explained that the project needs to be close to the electrical load it serves. Savion plans to lease the land for both sites. 

County Legislator Steve Englebright (D-Setauket) and town Councilmember Jonathan Kornreich (D-Stony Brook) empathized with their constituents. Englebright, who throughout his career has supported environmental initiatives, said the locations have been historically difficult places to fill, given the zoning as light industrial. 

“Something that is environmentally complicated and potentially harmful is not anything new to this area,” he said. Although he said he sympathizes with “all these correct uncertainties,” he added that residents have “to understand the larger context of what’s coming at us” in regards to the changing environment. 

In response to a question of who will bear the financial burden of damages in the case a fire hypothetically causes damage to surrounding properties, Thom Rainwater, director of development at Savion, said, “In the case of an incident the company will be responsible. Full stop.”