Save the date! Town of Brookhaven Supervisor Dan Panico along with Councilmember Jonathan Kornreich will host a Battery Energy Storage Systems (BESS) Community Forum at Suffolk County Community College’s Ammerman Campus, 533 College Road, Selden on Tuesday, Jan 21 in the Shea Theater, Islip Arts Building, from 7 p.m. to 9 p.m.

“This forum is a great opportunity to learn more about Battery Energy Storage Systems (BESS) and ask questions directly to a panel of experts. We want to hear your thoughts and concerns, so don’t miss out on this important discussion! For any questions, please call me at 631-451-6963,” said Councilmember Kornreich.

Paul Rogers from ESRG speaks to the civic association while Sid Bail stands before the podium and Key Capture Energy’s Phil Denara listens. Photo courtesy Stephanie Bail

By Samantha Rutt

Wading River Civic Association convened on May 23 to discuss a significant new development — a proposed battery energy storage system facility, known as BESS, on LIPA-owned property in Shoreham. The meeting, held at Wading River Congregational Church, drew a considerable crowd interested in learning about the project’s specifics and its implications for the community.

After concluding the business portion of the meeting, addressing new membership, voting rules and general notices, the civic’s focus shifted to the proposal from the Albany-based company, Key Capture Energy. 

Key Capture Energy is an independent power producer of utility-scale battery storage system projects. “Currently, in New York State, KCE operates three battery energy storage facilities — including the largest operational facility,” said Phil Denara, director of development at KCE. 

The company’s proposal is not the first Long Island has seen, as other companies with similar objectives have visited neighboring civic organizations and presented their systems. Indeed, KCE has plans for facilities at Babylon and Cutchogue. 

The increase in proposed battery energy storage facilities coincides with the Climate Leadership Protection Act, signed into law in 2019, essentially mandating greenhouse gas emissions to 40% by 2030 and no less than 85% by 2050 from 1990 levels. It also mandates 100% of electricity used in New York state must come from clean energy sources by 2040 with 70% renewable energy by 2030.

Project genesis and site selection

The discussion began with an explanation of the project’s origins and site selection process. The project was initiated to meet statewide goals for energy storage as Long Island transitions from fossil fuels to renewable energy sources. With a local demand for approximately 5,000 megawatts of electricity, integrating storage systems with renewable energy such as offshore wind and solar is crucial.

“Here on Long Island we currently have a demand for electricity to the tune of 5,000 megawatts and so as we transition away from fossil fuels and toward renewables, we have to keep that number in mind,” Denara said.

As explained by Denara at the meeting, in 2021 Long Island Power Authority issued a competitive solicitation for bulk energy storage projects, seeking at least 175 MW of capacity. Developers bid on various sites, including those offered by LIPA, which were strategically located next to existing infrastructure to reduce the need for new development. This site was awarded in August 2022 and is now moving from preliminary design to execution.

Project scope and capacity

The BESS project at Shoreham is slated to have a capacity of 50 MW, enough to power tens of thousands of homes. 

While this represents only 1% of Long Island’s total power demand, it plays a critical role in the broader transition to renewable energy. Currently, there are only two full-scale BESS facilities on Long Island, both with a capacity of 5 MW each, located in East Hampton and Montauk. The East Hampton facility has been out of commission since a fire on May 31, 2023.

Site details and development stages

The Shoreham site is situated on approximately 2.3 acres of land near the former Long Island Lighting Company property. Development has involved boundary surveys, geotechnical studies and comprehensive environmental reviews.

For completion, the project must navigate three main development components: land-use acquisition and permitting, grid interconnection and commercial power delivery contracts. The site benefits from exemptions from the Town of Brookhaven’s zoning requirements, although the developers are adhering to these standards voluntarily. Local officials, including the Town Board and emergency services, have been engaged throughout the process to ensure transparency and community safety.

Technology and safety considerations

BESS will employ advanced lithium-ion battery technology. A significant point of discussion was the safety of these systems. Lithium-ion batteries are chosen for their high efficiency, with a round-trip efficiency of about 90%, essential for storing and dispatching renewable energy.

Paul Rogers of the Energy Safety Response Group — comprising retired firefighters, service people, engineers and first responders responsible for handling codes, standards and safety protocols — detailed the safety measures in place. These include multilayered safety listings and comprehensive monitoring systems to prevent overcharging and overheating. The system’s design ensures that in the unlikely event of a failure, the issue remains contained within an individual unit, preventing any propagation.

Community concerns and future technologies

Civic members raised questions about the long-term viability and environmental impact of lithium-ion batteries. Some suggested exploring alternative technologies such as sodium-ion batteries. While the current focus is on lithium-ion due to its proven efficiency and safety, the developers remained open to integrating future advancements.

The project is designed for a 20-year operational life, with plans for recycling and repurposing battery components at the end of their lifecycle. This contributes to a circular supply chain, reducing reliance on international resources and enhancing energy independence.

The Shoreham BESS facility is set to become a critical component of the local energy infrastructure, promising enhanced reliability and sustainability for the community.

The civic association plans to continue these discussions in future meetings, ensuring ongoing community engagement and transparency as the project progresses. The next civic meeting will be held on June 27 at 7:30 p.m. at the Wading River Congregational Church. 

File photo

By Sabrina Artusa

New Leaf Energy has proposed a new battery energy storage system facility in Mount Sinai — a proposal that necessitates a rezoning of the current property.

The increase in development of battery energy storage systems in the state is part of the effort to achieve the goal of the 2019 New York State Climate Leadership and Community Protection Act, which states that by 2030, 70% of electricity should be derived from renewable energy. 

The battery energy storage system will work to offset the lack of wind and solar power during off seasons by storing excess electricity throughout the year, then release electricity when demand dictates. 

The facility will be approximately 40,000 square feet and will consist of 24 Tesla Megapack 2XL containers, and will generate around 80 megawatt-hours, which could power 16,000 homes. The proposed site is adjacent to Mount Sinai‒Coram Road and Route 25A.

The proposal was met with opposition from the community, many of whom were concerned that the facility, which consists of four battery installations, would provide a safety risk to the nearby school. 

In March, the developer approached the Mount Sinai Civic Association with their plans. At the civic’s May 6 meeting, New Leaf Energy prepared a presentation and answered questions. The meeting, according to the association’s president Brad Arrington, lasted two-and-a-half hours. 

Arrington estimated that of those who attended, 70-80% were opposed. 

“I think most people are concerned about the safety around BESS. They are worried about proximity to lithium and they are worried about fires,” Arrington said. “People are rightly concerned about that.”

A petition against the development listed safety concerns as a major reason why the facility should not be approved. While fires are a reasonable concern, New Leaf Energy’s systems have several safety measures to ensure any fires stay contained. 

However, the property is not zoned as a residential area, but as transitional business. The application from New Leaf Energy proposes a change to light industrial. 

According to their presentation, toxic gases are not a risk and precautions have been taken to limit the likelihood of fires. The units are spread out, have a thermal management system and on-site and remote monitoring systems. 

The civic expanded the conversation to include Mount Sinai School District and Mount Sinai Fire Department. Arrington said that the fire department seems “satisfied with the information they were provided” and have not “expressed significant concerns around safety.”

New Leaf Energy, in a PowerPoint presentation available on the civic website, has indicated there will be a community benefit agreement “in place of school district PILOT (payment in lieu of taxes),” which is estimated at “approx. $10,000 per year per project.”

The civic association is still gathering information and has not yet formed an opinion on the proposal. Arrington said the vote will likely take place in the fall. 

“We really try to represent the interests of our community to our elected officials and provide meaningful and balanced opinions to our officials,” he said.

Operation of the facility is estimated for summer 2027 if approved. 

Residents gather at the Heritage Center for a Mount Sinai Civic Association meeting. Photo courtesy Sarah Anker

By Sarah S. Anker

Over 100 residents gathered at the Heritage Center during a May 6 Mount Sinai Civic Association meeting to hear from New Leaf Energy, a battery storage company, about a proposed lithium-ion battery storage facility. 

According to the civic president, Brad Arrington, the plan to site the 20-megawatt battery storage system facility on a 1-acre parcel, located at the corner of Mount Sinai-Coram Road and Route 25A in Mount Sinai, has been in the works for seven years. Surprisingly, despite representing the area as a former Suffolk County legislator for the past 13 years, I only recently learned about this project.

Having facilitated the Green Homes and the Go Solar programs as the former director of Town of Brookhaven’s Office of Energy & Sustainability, I strongly support clean energy initiatives. However, I have concerns about the proposed location of this facility. Placing it on a 1-acre parcel with no buffers, near one of the county’s most accident-prone intersections, raises red flags. Additionally, the site is close to residential neighborhoods, a public walking path, an SCWA drinking water well and Mount Sinai schools.

I would have no problem if the siting were in an area that, if the units were to catch on fire, there would be less exposure to the highly toxic fumes emitted. After the East Hampton battery storage facility caught on fire, several towns — including Southampton, Southold and Huntington — moved forward with moratoriums. It is only common sense that more scrutiny be done to address the safety of these facilities and where they are placed. 

Gov. Kathy Hochul (D) has created the Inter-Agency Fire Safety Working Group to review the issue of battery storage systems safety. As the working group investigates the fires that have occurred at three New York locations, a moratorium is needed in Brookhaven to ensure the safety of its residents. 

Over 20 years ago, a Home Depot was proposed to be built on the site that is now Mount Sinai’s centerpiece, the North Shore Heritage Park. We fought hard to create the park by collecting petitions, writing letters to our elected officials, wrapping green ribbons around our mailboxes and rallying our community together. Can you image if no one cared back then, and a Home Depot was built? Eighteen-wheeler trucks would snarl traffic, the green rolling hills would be black pavement and the memories of community concerts, holiday events, sports games and the springtime daffodil smiling face on the hill would be lost. 

Just as location, location, location is what the realtors say when emphasizing the value of real estate, let’s also consider the location of this project and the value we place on public safety and quality of life. Do we really want an industrial parcel located in the heart of our hometown? The project cannot move forward until the Town Board votes to change the zoning to light industrial. I encourage residents to attend upcoming Town Board meetings and provide input before a decision is made. Government is here for you when they hear from you. 

Sarah Anker (D-Mount Sinai) is a District 1 candidate for the New York State Senate and was formerly a Suffolk County legislator.