The Rocky Point Fire Department Company 2 is using a warehouse on Prince Road as its main base. Photo by Kyle Barr

Changes are happening for the Rocky Point Fire Department Company 2, otherwise known as the Black Sheep Company, as the fire district finally settles in to replace the aging firehouse on King Road in Rocky Point.

The night of May 1 the company moved all its equipment and vehicles into one of the warehouses of what was once the Thurber Lumber Yard property. The warehouse has enough room to fit the ladder truck, fire engine, brush truck, two EMS vehicles, and will also be home base for around 40 volunteers. The dirt road out of the property leads onto Prince Road, just a five-minute walk from the old firehouse.

The Rocky Point firehouse on King Road in Rocky Point. File photo by Kevin Redding

Anthony Gallino, the chairman of the board of fire commissioners, said they were lucky to get those trucks in such a close location.

“It would have been a big problem for us,” Gallino said. “We might have been able to relocate some of the equipment into the other firehouses and pulling certain stuff not used as frequently and leaving it out. This is just a block away, and response times probably won’t change at all.”

Mark Baisch, the owner of Landmark Properties and the old Thurber property, said he was approached by the department and didn’t hesitate to offer one of the buildings for free for the fire company’s use. While plans are still in motion to break ground on 40 one-bedroom apartments for seniors, he said the fire department being in that building won’t disturb that development.

“We’ll work around them,” Baisch said.

District manager Ed Brooks said the deconstruction will start May 13 with asbestos removal, which could take from two to three weeks. Once inspection of the building is completed, demolition will begin, and that could take a number of weeks before construction on the new firehouse truly begins. Overall construction could take upward of a year, according to Gallino.

Citing that the aging firehouse, built in the 1950s, had received little upgrades and attention for half a century, the district proposed a $7,250,000 firehouse project that was approved by residents 204 to 197 in an August 2017 vote. Also approved in a separate vote were plans for the purchase of a new ladder truck at a cost of $1,250,000. While plans were originally set to break ground in early 2018, Brooks said the first set of bids came in too high for the project, and when the district put in for a new set of bids, too few came in. The fire district has since changed construction managers and has settled on a new set of bids. The new ladder truck won’t be purchased until after construction of the future firehouse is finished.

The board chairman said the new firehouse is especially important as the community grows.

“This is just a block away, and response times probably won’t change at all.”

— Anthony Gallino

“The other building was outdated, heating and air conditioning was a problem, the bays were so tight that when trucks were moving out, the guys were changing just a foot from a truck coming in and out,” Gallino said. “It’s a conservative building, but it will suit our needs.”

Members and friends of the Black Sheep Company took to Facebook to commiserate about their old firehouse as they moved into the warehouse on Prince Road.

“Tonight is a bittersweet night for the North Shore Beach Fire Company [as] we said goodbye to our firehouse,” local resident Theresa Lattman wrote in a Facebook post May 1. “Our trucks pulled out for the last time, but a new firehouse will be built in its place that will hopefully serve this community for a long time.”