Brookhaven Supervisor Ed Romaine and the town board have taken steps that would allow the construction of a power plant in Yaphank, complicating the status of Port Jefferson's LIPA-run plant. File photos by Alex Petroski

It’s one step forward, two steps back for Caithness Energy, LLC in Brookhaven.

After securing a win in its efforts to advance the construction of a 600-megawatt power plant in Yaphank earlier this month, Caithness Energy LLC, an independent, privately held power producer informed by Brookhaven Town its special use permit for the site expired July 15.

The special use permit, initially approved in 2014,  granted Caithness permission to build a power plant on the site, according to Town Attorney Annette Eaderesto. It was granted for two years and  one-year extensions were approved twice, which is the limit under town law.

“We’re looking into it, but believe it has no bearing and we look forward to the next steps before the Planning Board,” Caithness President Ross Ain said in a statement.

The possibility that the permit might have expired was first raised by Councilwoman Valerie Cartright (D-Port Jefferson Station) during a July 12 meeting. She abstained from voting on a motion to lift a restrictive covenant preventing the project’s advancement due to amendments made to Caithness’ original 2014 plans, which included a reduction to the plant’s output capacity and updated technology. The other five councilmembers and Supervisor Ed Romaine (R) voted to remove the covenant.

“They’ll have to file a new application for the special permit and we’ll certainly accept it,” Eaderesto said.
The town attorney noted Caithness still has a pending site plan application before the Planning Board, which would remain as such as a new special use permit is sought.

The proposed project has drawn opposition for its potential environmental impact from groups like Sierra Club Long Island and state Assemblyman Steve Englebright (D-Setauket).

In addition, Port Jefferson Village Mayor Margot Garant has spoken out against the proposal, warning the construction of a second Caithness plant could push her community “off the economic cliff.”

The village has argued a way to make good with Long Island Power Authority over its decreasingly needed plant — and LIPA’s legal contention its Port Jeff plant’s property tax value is over-assessed and has been for years — could be to increase its output capacity. If constructed, the Caithness II plant, which would be built nearby the company’s first Yaphank plant opened in 2009, could theoretically kill plans to repower the Port Jefferson plan, according to the village.

Port Jeff Village and the town have said a settlement is nearing in an eight-year-long legal fight with LIPA, that will likely result in a gradual decrease in revenue from the plant’s property taxes, which help fund budgets for the village, Port Jefferson School District, the fire department and the public library.