Miller Place Superintendent Marianne Cartisano and board of education President Johanna Testa look over captial projects for the coming summer. Photo by Kyle Barr

Miller Place school district officials are looking to perform some lasting modifications to some of their schools’ infrastructure, as discussed at the Nov. 14 board of education meeting.

Summer 2019 will bring new ceiling lighting to the Laddie A. Decker Sound Beach School, a new 6,000-gallon fuel oil tank for the high school, replacing the existing 15,000-gallon tank, as well as replacing asbestos-ridden floor tiles existing in several classrooms at the high school.

The entire project will cost $500,000, with $400,000 coming from the district’s capital funds, according to officials. Another $100,000 will come from state funds secured by state Sen. Ken LaValle (R-Port Jefferson).

Rocky Point-based architect Michael Guido, the district’s retained architect, told the Miller Place school board that with the inclusion of gas service lines recently installed in the school it no longer has need of such a large tank, thus the scale down.

Superintendent Marianne Cartisano said the existing floor tiles containing asbestos were installed back when the high school was built, and they exist in several classrooms throughout the building. While she said they don’t pose any harm to students currently, they will be removed during the summer when there are no students in the classrooms.

“It’s not a dangerous situation at all, but while we’re doing work in the building we’re going to go in and replace some floor tiles,” she said.

The new lighting at  Laddie A. Decker will include new ceiling structural support and new, brighter LED lighting.

Guido said the bids for all projects will go out from Jan. 3 through 16, and they anticipate awarding the bid Jan. 23. The work for all buildings will be done during the upcoming summer, and district officials said they would work to make sure construction does not impede summer programs.

Mount Sinai’s administration and board — including Superintendent Gordon Brosdal and BOE President Robert Sweeney — will ask taxpayers to weigh in on a capital bond proposal Dec. 11. File photo by Erika Karp

The Mount Sinai School District board of education has announced a $25 million price tag for its upcoming capital bond proposal, which would make major repairs to school roofs as well as add new teaching spaces.

At its Oct. 11 meeting Mount Sinai’s board voted to move ahead with the $25,331,498 bond proposal and set a date for a community vote on Dec. 11.

The board showcased the final bond proposal at its Oct. 17 meeting for the community, which proposes an average $240 tax increase on a home assessed at $3,700, or $370 on a home with an assessed value of $5,700.

The bond has changed somewhat since its initial presentation Sept. 26. The sticker price has gone from $24.6 million to $25.3 million and new projects have been added, including upgrades to the boys and girls bathrooms in both the middle and high school. Other additions included creating a girls varsity softball synthetic turf field for $327,750 and a boys varsity baseball synthetic turf infield for $393,300.

The original bond proposal included new additions to the high school orchestra room and a 12,000 square foot fitness center, but those were not included in the final proposal. The September proposal also included a new music lab, but board President Robert Sweeney said the school did not have the space for it, and that additions to the bond were made based on student enrollment, which is expected to decrease in the next several years.

“In four years, there will be 200 less kids in the high school than we’ve ever had,” Sweeney said. “This [bond] is driven by student need and it’s student centered.”

The bond would also fund additional security improvements, including adding security cameras to all school buildings as well as replacing exterior doors and adding non-ballistic security film to windows.

In terms of repairs, the bond would use $2.1 million to complete 54,000 square feet of roofing replacement for the high school, and would also fund projects to repave the high school’s main parking lot, replace flooring in the middle school and replace the public address and master time clock system in all school buildings.

Superintendent Gordon Brosdal said the most important inclusions were those that repaired some of the campus’ aging buildings.

“I think the board did a great job to weigh everything out and keep the community in mind, especially repairing our 40-year-old, 50-year-old, 60-year-old buildings,” Brosdal said.

The bond also includes funds for one synthetic turf multi-purpose field and 1,400 square foot locker room renovations and expansions at the high school.

Sweeney said the board took out multiple items from the original proposal, including repairs to masonry, painting lintels and for the inclusion of natural gas emergency generators for the elementary and middle school because several of those projects can be included in either future capital projects using the district’s unassigned fund balance or with normal district budgets.

“Those items were perfectly fine, but we have money in the budget to do it,” Sweeney said.

Some community members, like Mount Sinai resident Michael McGuire, have questioned the need for a bond if it also leads to tax increases.

“The kids we are investing in cannot afford to live here,” McGuire said.

Voters can weigh in on the referendum Dec. 11. Residents in the school district must be registered in order to vote. Residents can register at the District Office during school hours from 9 a.m. to 4 p.m. through Dec. 5.

Mount Sinai High School. File photo by Kevin Redding

The Mount Sinai School District is asking the community to pay higher taxes in exchange for upgrades to its buildings.

The district unveiled a capital projects proposal that will require passage of a bond by the community at a board meeting Sept. 26. The list of projects contains a number of renovations and upgrades officials hope will keep MS schools in line with other local districts and prepare its facilities for future generations.

“We’re not looking to do this all for tomorrow – we’re looking for providing for our kids 10 to 15 years from now,” board of education President Robert Sweeney said.

The planned total for the bond currently sits at $24,695,663, which would raise taxes by $235 for a household in the Mount Sinai community with an assessed value of $3,700, or $362 for an assessed value of $5,700, for example. This tax increase will be in addition to whatever tax value will be released for the 2019-20 budget.

Items to be included in the more than $24 million in projects are a large swathe of renovations and repair work to all three of the school buildings on campus, as well as the athletic fields and grounds. The bond proposal seeks to replace the public address and master time clock system across all three buildings. In addition, it asks for money to replace several exterior doors, windows and heating, ventilation and air conditioning systems across all school buildings on the campus.

In line with the district’s push for stronger building security, the bond details a number of security upgrades, including new surveillance cameras and intercom systems, exterior door automatic locking systems and film-lined glass windows to make it more difficult to see in.

The high school is receiving a substantial share of attention, with funds in the bond to finish replacement of the roof, which has long suffered from leaks. It also calls for the construction of new music practice rooms along with renovations to the art room, ceramics room, fashion/tech room, locker rooms and science labs.

In terms of outdoor facilities, the bond proposes two new field surfaces, one a multipurpose turf field at the high school and another a natural surface girls softball field.

The board will hold a special meeting Oct. 10 to discuss the merits of certain projects on the list. Sweeney said he wanted to be careful to only go out to bond for projects the district wouldn’t normally be able to complete with excess fund balance.

“If I can pay for it, why should I put it on credit?” he said.

The board also detailed a number of potential projects not included on the main list to be discussed prior to approving a final menu, like replacing stage lighting at Mount Sinai Elementary School and reconfiguring the library in the middle school. The high school could see the auditorium seating replaced along with additions to the orchestra room and the main office. The biggest extra projects included the construction of a new 6,500-square-foot maintenance storage garage and the creation of two new synthetic turf fields, one for softball and another for baseball.

The total for the additional projects is about $26 million. If the district were to include everything from additional projects and the bond as currently proposed, the total would equal $50,483,500, which would add $480 or $740 per year in additional taxes for homes assessed at $3,700 or $5,700, respectively.

Board Vice President Lynn Jordan said that several months ago the original list of projects provided to the board equaled close to $68 million, and she thought the 20 Mount Sinai residents and school employees on a bond committee formed during the summer did a good job in focusing down on what was most critical.

“They put their hearts and souls into this, and I’m very impressed with how they all handled deliberations,” Jordan said.

Mount Sinai resident Brad Arrington said he hoped the school would be conscientious not to make extensive changes just to keep up with other local school districts.

“It can be easy to feel envious of what other districts have, but we need to focus on what we can afford,” Arrington said. “We need to take a balanced approach, with some of our focus dedicated to sports, some to the arts.”

In May district residents approved a $5 million capital project referendum. The funds have already gone toward finishing refurbishing the school’s football field, and replacing perimeter fencing and fixing a portion of the high school roof is also underway.

Residents are encouraged to attend or send in comments to the board before the Oct. 10 meeting.

Once the board votes to approve the bond, there will be a mandated 45-day period before the bond can be brought to a community vote. The board will determine when a vote will be held after its Oct. 27 board meeting.

by -
0 63
Port Jefferson High School. File photo by Elana Glowatz

Most school district administrators and staff, like students and teachers, are able to take the summer to recharge and unwind. In Port Jefferson School District, Fred Koelbel, director of facilities and transportation, gets no such respite.

The overseer of all things buildings and grounds in the district was at the Sept. 17 board of education meeting to fill the board and the public in on the work done during the summer months and beyond. Some projects were completed using capital reserves while others were handled “in-house” by district employees, though virtually all were completed prior to the start of the 2018-19 school year.

“We had the opportunity to see a lot of these improvements firsthand, and I certainly would commend the staff that worked on them, it was impressive,” board President Kathleen Brennan said.

Koelbel spoke about some of the bigger projects accomplished by his team of workers.

“The biggest project we undertook, and it actually started before the summer, was the complete renovation of the electrical distribution system in the high school,” Koelbel said.

Beginning during spring break, Hauppauge-based All Service Electric Inc. re-fed power lines through underground trenches. Previously, power lines from outdoor polls into the school were fed along overhead lines, susceptible to the elements and to trees. The job was completed during the summer.

“This did two things for us — now if our power goes out, part of the grid went out and we’re much higher priority to get restored,” Koelbel said. “Before when it was, a tree knocked down a line on our property, it was just our property was out, and the neighborhood might still be on and we might not be as high of a priority. But now we also have more reliable service because it’s underground, so it’s not affected by the trees.”

He said the task wasn’t easy for the vendor and commended the job.

“It snowed on them, it rained, the trenches filled up with water, their boots were getting stuck in the mud and the clay, but they persevered and got lines in,” he said. “We couldn’t be happier with the work they did.”

The new underground feeds will soon also house the school’s cable and phone lines, eliminating the need for any cables fed to the school overhead.

Many of the projects were simpler to complete, though not necessarily less time consuming. The high school track was torn up and resurfaced. The second phase of a multiyear roof replacement project continued. Sidewalks in front of the high school were replaced, as were crumbling bricks in the façade of the exterior of the building. The section of the high school driveway nearest to the main entrance on Barnum Avenue was repaved.

One of the more visually noticeable upgrades took place in the high school gymnasium. Koelbel said a new sound system and video board were installed, and the walls were repainted purple and white.

“It really has a flavor of ‘welcome to our house,’” he said of the refurbished gym.

In the elementary school, the floors of two classrooms were removed and replaced, as were the carpeted floors in a couple of hallways.

“It’s like a huge Petri dish, it’s not a good choice,” he said of carpeting in elementary school hallways, which was replaced with tile flooring.

Several doors to classrooms in the elementary school were replaced as part of another multiyear implementation, as many were beginning to show their age, according to Koelbel. Door locks in both school buildings were upgraded as well.

Blinds on the windows of classrooms in both buildings were replaced with rolling shades. Additional security cameras were added across district buildings, as were fire extinguishers for every classroom, and several fire alarms were also upgraded at the high school.

District Superintendent Paul Casciano and Assistant Superintendent Sean Leister each commended Koelbel and the district’s staff for completing the projects in time for the start of school.

by -
0 2446
Significant upgrades are underway for Mount Sinai’s football field, bleachers, track, press box and surrounding areas. Photo by Kyle Barr

The Mount Sinai Mustangs football team will soon be cantering down a new turf field as part of the school district’s ongoing capital bond projects.

By the end of the school year, the district hopes to have completed an upgrade to its turf field, track, concrete plazas, fencing, press box and bleachers for the varsity field. Plans are also in place to repair the high school roof as part of the district’s $5 million capital project that was approved in May by residents with a 787 to 176 vote. The district hired Melville-based architectural and engineering firm H2M to help design the new sports amenities and fencing, and Superintendent Gordon Brosdal said right now all projects are on or ahead of schedule.

“You have to take care of your houses — all your stuff,“ Brosdal said. “If you don’t maintain them it becomes a big expense.”

The district has ripped up its old turf surface, fearing that its age could result in it being condemned, and replaced it with a new one that prominently shows the school logo and mascot name. Amityville-based The Landtek Group Inc. is currently building the new track and new concrete plaza that will border the football field, both of which will be finished by mid-November.

The new upgraded bleachers and press box should arrive in mid-November as well, according to district officials. The total amount for the athletics upgrades, including the new field and amenities, cost about $2.3 million.

Brosdal said the field would be finished by Sept. 21 when the Mustangs will be hosting its first home game against Port Jefferson.

“We tried to schedule the start of our season to be away games, but we should definitely be ready by that date,” Brosdal said.

About $1.4 million went to fixing a patch of the high school roof that has caused problems for the building during rainstorms. Construction will take place after school hours and is expected to be completed from late October to mid-November.

The district is also planning to invest in new perimeter fencing. Some parts will be amending torn down chain link fencing, some of which borders residential properties. For fencing that borders the road, the plan is to build “ornamental” black iron fence to match the rustic character of the surrounding area. This includes a new gate stretched across the school’s front entrance off Route 25A with stone supports that will match the electronic signs stationed at both entrances.

The fences, along with other security measures, cost the district $800,000. The plan is to start construction in late September and is expected to be completed by mid-November.

Several new security updates have finally come at the start of the new school year as well, though not part of the capital project. All faculty must wear security badges that are color coded to their school building. Athletics personnel have a purple badge while substitute teachers are yellow. High school students must also now wear badges, colored differently depending on their class year.

The badges and guard booth were not part of the capital project and were instead included in the district’s security funding in the general fund budget. Mount Sinai’s 2018-19 budget included $400,000 in security funding, which was $305,000 more than the 2017-18 school year.

Students and staff are now required to scan their badge into an electronic system upon entry. To go along with this change, a new front gate guard booth was installed in May that is wired with a phone, computer and cameras. Persons approaching the front gate need to either show a driver’s license or school badge to gain access to the campus.

by -
0 78
Rocky Point High School. File photo by Desirée Keegan

The Rocky Point school district is battening down the hatches and shoring up its defenses with money from its ongoing capital bond project.

The newly renovated music room in the high school. Photo from Rocky Point

The district has finished phase 2 of its list of projects set after passing a 2016 bond proposal. Much of the work has already been completed, including replacing the aging ceiling and lighting in much of the district’s four school buildings.

“What we did weren’t things that are exciting like adding on a new wing, new classrooms or a new gymnasium, they were basic things to keep serving the students,” Superintendent Michael Ring said.

In 2016 Rocky Point residents voted to let the district borrow $16 million for upgrades and repairs. The first half of the project, amounting to roughly $7 million, was completed in summer 2017. Parts of the second half of the plan, costing approximately $9 million, were completed before the start of the school year Sept. 4, according to the district.

In 2017, residents also approved with a 600 to 312 vote to release $3.4 million in capital reserve funds to work in tandem with the bond projects. That money was used to renovate the district’s music classrooms as well as finishing resealing of the middle school’s exterior brickwork to prevent water penetration. There are also plans for a future reconfiguration of the roadways on middle and high school property. Work is ongoing to refurbish the turf on the high school’s lower field, but Ring said weather has delayed the project. He said it should be completed within the next few weeks.

Renovated locker rooms at Rocky Point High School. Photo from Rocky Point

Last year’s bond work included new boilers and renovated bathrooms at the Joseph A. Edgar Elementary School, as well as adding air conditioning to the high school auditorium. Summer 2018 construction, overseen by Huntington Station-based Park East Construction Corp., provided renovations to the high school’s boys and girls locker rooms and bathrooms. An Americans With Disabilities Act-compliant lift for the high school gym stage was also installed. Along with the work at the high school, the Frank J. Carasiti Elementary School cafeteria had new air conditioning installed.

Ring said the most substantial improvement to district buildings during the past summer was the installation of new LED lighting fixtures throughout the high school and JAE elementary. The new lighting should be more energy efficient, he said, while giving the school the opportunity to replace aging ceiling tiles in places that had not been addressed for close to 50 years, since the high school was constructed.

Work to renovate the middle school’s lighting system will take place during the year after school hours. FJC elementary has had its lighting replaced in the building’s corridors, and the rest of the building’s lighting will be updated in summer 2019.

These lighting fixtures include new “daylight harvesting technology” that will dim the lights depending upon the amount of natural light that enters the room, which Ring said should save on electrical costs. The new lights also have occupancy sensors that will shut off all lights if there is nobody in the room.

“That’s so you don’t see that effect you see when you’re driving down the road and the whole building is lit up, even if it’s 8 o’clock at night,” Ring said.

Newly installed LED hallway lighting at Frank J. Carasiti Elementary School. Photo from Rocky Point

As part of the bond project, the district is also looking to beef up security at its buildings. The district added unarmed security guards to school buildings for the start of the new school year. Rocky Point is also looking to implement a new door access system to reject unwanted intruders as well as “door-ajar systems” that will notify the school if a door is being propped open from the inside.

The district also wants to improve its security camera capabilities by adding more camera coverage as well as installing new facial recognition and license plate reading technology. Ring said those projects are currently on hold awaiting New York State approval. If approved, the district will immediately put proposals out for bid so construction of those security additions can begin before the end of the 2018-19 school year, according to the superintendent.

Ring said he happy with the results of the bond work so far, even as it became stressful to finish ongoing projects before students returned for the start of classes.

“It’s always a relief when it’s done because it’s always a stressful time,” Ring said. “When you look at the end of June and things are getting pulled apart, then hoping and praying they get put back together for September. Hopefully next year’s project will come along, and the same thing will happen.”

Comsewogue board of education President John Swenning and the rest of the board unanimously passed a resolution to establish a $32M bond referendum in May. File photo by Erika Karp

Comsewogue School District is going to ask taxpayers for a little more when they head to the polls in May.

The board of education approved a resolution with a unanimous vote at its March 5 meeting to officially add a referendum on a $32 million spending plan recommended by the district’s Facilities Committee in February. The list of slated upgrades and improvements is more than 100 items long and addresses areas in each of Comsewogue’s six buildings. If passed, the money would go toward improving health and safety, infrastructure, academics, arts and athletics.

“The proposed facility improvements preserve the integrity of the school buildings, address repairs, improve
instructional resources for all and upgrade athletic facilities,” district administration said in a statement.

The list of areas in need of improvement was the byproduct of several meetings and discussions by the committee, a group of 21 professionals from across the Comsewogue community including members of the board, administrators, architects, engineers, former teachers and civic association members. The group was assembled in early January and had been tasked with presenting recommendations to the board.

“I just want to say thank you to the Facilities Committee that spent a lot of time going through our buildings,” board president John Swenning said during the meeting. “This bond was brought to us from the community members. They found what they felt needs to be addressed and they came and presented it to the board. We’re going to accept it just as the committee has submitted it to us.”

Some of the projects include required upgrades to achieve compliance with the Americans with Disabilities Act; repairing parking lots and sidewalks; adding security vestibules at all of the district buildings; fixes to exterior and interior building infrastructure; improving athletic fields and facilities; and kitchen upgrades. If approved by voters, the bond would have a 15-year life with about $3 million in interest. Some of the higher-priced projects included in the committee’s recommendation are: a new roof with solar panels at Terryville Road Elementary School; interior work at John F. Kennedy Middle School, including some classroom and hallway renovations; and upgrades to the high school concession stand building. If passed, the average taxpayer would see an increase of about $120 annually to their school tax bill, based on conservative state aid estimates, which won’t be known until the spring.

“We’ve really touched everywhere that your child could be, from safety in the parking lots and curbs, to every elementary classroom getting a face-lift,” said Stephanie Jaklitsch, a former teacher in the district who also has children attending Comsewogue schools. Jaklitsch is a member of the Facilities Committee and was among the contingent who presented recommendations to the board Feb. 12. “Our students are going to see changes all the way through their education.”

The bond vote will be held at the same place and time as the annual operating budget vote and school board trustee elections. Polls will be open at Comsewogue High School May 15 from 9 a.m. to 9 p.m. The district has suggested it will hold informational meetings going forward to get the community up to speed on the contents of the bond.

File photo

The Comsewogue board of education had a community bonding experience Feb. 12.

The school district’s six buildings are in need of upgrades and improvements, according to its facilities committee, a group of 21 professionals from across Comsewogue including members of the board, administrators, architects, engineers, former teachers, civic association members and more. The group was assembled in early January, and has been holding workshops and meetings to compile a list of projects to recommend to the board.

The committee presented a list of more than 100 upgrades considered of the highest priority and identified as the A-list. The projects would take place in each of the district’s schools if a bond referendum were passed. Some of the projects include required upgrades to achieve compliance with the Americans with Disabilities Act; parking lots and sidewalks; security at all of the district buildings; exterior and interior building infrastructure; athletic fields and facilities; and kitchen upgrades among many others.

The total price tag for the A-list would be almost $32 million, paid for during a 15-year period with approximately $3 million in interest, according to the committee. If passed, the average taxpayer would see an increase of about $120 annually to their school tax bill, based on conservative state aid estimates which won’t be known until the spring.

The committee also presented two other potential propositions for the board to consider: one a $9 million B-list of items deemed to be of lower priority and the third a complete overhaul of just the district’s air-conditioning units for approximately $13 million. Members of the committee said after touring the district facilities and buildings, its initial list of projects was in the ballpark of $75 million, which it then pared down to what currently appears on the A-list.

Susan Casali, the district’s assistant superintendent for business, served as the leader of the facilities committee.

“They’ve been phenomenal,” Casali said, of her colleagues on the committee. “It has been a great process, a lot of input, a lot of knowledge. We went through a lot of things and they really worked hard.”

Casali said the committee also took public input along the way from teachers, organizations and others in the community who had requests for upgrades.

“The board needs to know, and the public should know, how very carefully we looked at what items were to make the A-list,” said Joan Nickeson, a member of the Facilities Committee engaged in several aspects of the Comsewogue community. Nickeson also praised the work on the committee of architect Kenneth Schupner and engineer Frederick Seeba.

“The engineers and the architects, I don’t know how well you know these gentlemen, but I was so impressed with their knowledge and their ability to handle a myriad of questions,” she said. “We looked so carefully at every item.”

Stephanie Jaklitsch, a former teacher in the district who also has children attending Comsewogue schools, offered her input as a member of the committee.

“We’ve really touched everywhere that your child could be from safety in the parking lots and curbs, to every elementary classroom getting a face-lift,” she said. “Our students are going to see changes all the way through their education.”

Board of education president John Swenning, and Superintendent Joe Rella each thanked the committee for its thorough work, dedication to improving the Comsewogue environment and generosity in lending each of their personal levels of expertise to the group.

Some of the higher-priced projects included in the committee’s recommendation are: a new roof including solar panels at Terryville Road Elementary School; interior work at JFK Middle School, including some classroom and hallway renovations; and athletic upgrades at the high school to the
concession stand building.

The board will vote March 5 on the recommendations, and if it elects to move forward, to establish the specifics of the bond referendum and how it would appear on a ballot. The referendum would be included as a separate proposition on the same ballot as the annual budget and school board vote to be held May 15.

The full list of project recommendations is expected to be posted and available on the district website, www.comsewogue.k12.ny.us.

This post was updated Feb. 14 for grammatical fixes.

by -
0 48
File photo by Elana Glowatz

The Port Jefferson School District has its sights set on a massive face-lift that would impact all of its buildings, but it will come at a substantial cost.

District administration presented a $30 million capital bond proposal to the board of education and the public during a board meeting Sept. 12 which would feature a three-story addition to a wing of the high school, additional classrooms at the high school and elementary school, a turf football field at the high school and lights for the elementary school field, and many more improvements. The district’s total budget for the 2017-18 school year is about $43 million total.

Proposal highlights

•$7.6M to construct a three-story addition at PJHS

•$2.3M to construct new music room and instrumental practice room at PJHS

•$2.2M to build addition to PJHS cafeteria and renovate kitchen space

•$1.2M to replace windows at PJHS

•$2.5M to construct two additional classrooms at elementary school

•$1.7M for locker room renovations at PJHS

•$1.6M for installation of stadium lighting at Scraggy Hill fields

•$1.4M for a new synthetic turf football field at PJHS

•$3.7M to convert tech ed building to new central administration headquarters

•$1.6M to install drainage walls at north side of middle school building

The district will need community approval on a referendum currently slated for a vote Dec. 5 to be able to proceed with obtaining the bond and ultimately beginning construction. If approved the construction would tentatively begin in 2019 and payments would be made annually beginning at about $1.5 million and concluding with a final $2.5 million installment in the 2033-34 fiscal year. The project would result in a homeowner who pays $4,000 annually in school taxes being asked to contribute an additional $200 per year. The district plans to post a “school tax calculator” tool on its website in the coming weeks to allow residents to check how much their tax bill would increase with the additional $30 million burden, on an individual basis. The ask comes at a time of financial uncertainty for the district, which along with several other municipalities on Long Island could potentially lose a substantial amount of property tax revenue pending the outcome of a lawsuit against the Long Island Power Authority.

“Regardless of what happens with LIPA, we to need to take care of the schools,” District Superintendent Paul Casciano said during the meeting. “The best investment you can make, and I know I’m a public school educator so you expect me to say stuff like this, but the best investment you can make is in your schools, and it affects your property values. To neglect the schools is not really a wise move in terms of investment.”

Port Jefferson resident Drew Biondo was one of several community members in attendance who expressed concerns about an “all or nothing” referendum, as he said he viewed some of the components of the proposal as vital and others as less urgent. Casciano and Deputy Superintendent Sean Leister both said during the meeting the district hadn’t yet decided how the referendum would appear on the ballot, be it broken up into more than one component to be voted on or a straight, “yes” or “no” vote on the proposal in its entirety.

“I’d have to think hard about a turf field and lights,” Biondo said. “I understand the need, but when we’re facing possible closure of a power plant … I haven’t made a decision, but one of the things that will probably sway me is if this is an all or nothing. If it’s all or nothing, I don’t know which way I’ll go.”

The district is seeking more community input on the proposal through a survey on its website which was originally going to close Sept. 15, though Casciano said it may be left open for longer. Public tours will be held Sept. 20 at 6 p.m. at the elementary school and Sept. 25 at 6 p.m. at the high school for those interested in seeing the areas designated for upgrades.

UPDATE: The district has extended the window for community members to complete the bond proposal survey on its website through Oct. 9.

A plan for what the new concession stand at Kings Park High School would look like. Images from Kings Park school district.

By Jenna Lennon

Although Kings Park school district is ready to get to work, summer improvements have not yet begun due to delays from the state.

Phase two of the proposed five-year renovation plan for Kings Park is still waiting for approval from the State Education Department. The construction originally scheduled to begin in the summer months will now have to be extended into the fall and spring semesters even though plans were originally submitted back in October, 2016.

Tim Eagen, superintendent of the Kings Park Central School District, said the school will try to minimize possible inconveniences due to the construction as best as it can.

“We anticipate getting all the work done; probably not all of it done during the summer,” he said in an interview. “Some of it is going to extend out into the fall. Some of it we’ll do during shut downs during the course of the school year.”

Eagen said some projects will not be too difficult to complete during the year, but that’s not true for all.

“One of the pieces, for example, is a door replacement project that can just happen nights and evenings and weekends during the school,” he said. “Probably the biggest visual piece that’s going to be delayed is for the track and the field. We have a concession stand with bathrooms that’s planned. It’s looking like that’s going to flip to the spring.”

Like last summer, improvements have been planned for every school in the district. Here is a breakdown of the specific projects happening at every school.

Kings Park High School:

Track/field lighting

Concession stand with bathroom

Library media center renovations

Auditorium seating/flooring upgrades

Electrical distribution and switchgear

Emergency power supply

Parking lot pavement upgrades

Air conditioning for auditorium and main gymnasium

William T. Rogers Middle School:

Field irrigation

Locker room renovations: new lockers

Gymnasium renovations: bleachers and electric for blackboards

R.J.O. Intermediate School:

Asphalt and pavement upgrades

Interior renovations: flooring (including asbestos removal)

Auditorium upgrades: seating and flooring

Interior renovations: ceilings

Electrical distribution and switchgear

Park View Elementary School:

Asphalt and pavement upgrades

Masonry restoration

Interior renovations: flooring (including asbestos removal)

Door and hardware replacement

Electrical distribution and switchgear

Plumbing upgrades

Toilet renovations

Boiler upgrades

HVAC and controls

 

Updated July 18: 

Egan said he received approval for RJO Intermediate School late last week, and Park View Elementary Monday, July 17.

“We are still waiting for final approval for the high school and middle school projects,” he said in a email. “They have passed the architectural review but still in the engineering review phase.”