Comsewogue displays progress on bond work
Students will walk through security vestibules come first school day
With $32 million in the Comsewogue school district’s pocket from a recently passed bond, school buildings are seeing various amounts of renovation and reconstruction throughout
the district.

Phase I is a $5.8 million chunk of the $32 million, which voters approved 768 to 315 back in 2018. Work is well on its way this summer, with projects going on in all six of the district’s educational facilities, many of which focus around the same theme, security vestibules.
“They are security traps, so there is a staging area between the two doors,” said Susan Casali, associate superintendent.
Vestibules are being installed in each of the six buildings, though they’re not uniform in shape and design, having to mold around the current entrances. In the Terryville Road Elementary School, the building’s office is being moved closer to the entrance to allow for windowed access into the vestibule, “like you would see at a bank,” Casali said.

This works with the school’s Raptor Visitor Management System, a web-based monitoring software designed to track visitors and electronically check them against public databases. In addition, all employees now use lanyards that can be scanned at the schools’ front entrances to gain access to
school buildings.
All vestibules are expected to contain bullet-resistant glass. It was something that school officials said was part of the planned bond project during committee even before the Marjory Stoneman Douglas High School shooting in Parkland, Florida, last year. That particular shooting set off a wave of calls for increased school security. If the glass is not installed by the time school starts Sept. 3, the district plans to install it before Jan. 1, 2020.
“We wanted to really increase our security,” Casali said.

Other than the vestibules, this year’s part of the bond project includes repaving the parking lots and replacing sidewalks at Terryville Road Elementary School and Boyle Road Elementary School. At Terryville, the work has created an additional parking lot for school staff on the north end of the lot, as well as replacing the cafeteria flooring for asbestos abatement. This accounts for a large portion of Phase I funds, with work at Terryville and Boyle costing a combined total of $2,733,435.
All elementary schools will see new kitchen equipment, including a new kitchen walk-in cooler at Terryville and gas conversion and cooled condenser, replacing an old freezer and refrigerator at Boyle Road, Clinton Avenue Elementary and Norwood Avenue Elementary. Norwood will also be getting a replaced kitchen ceiling and serving line reconfiguration. The high school kitchen and cafeteria ceilings are also being replaced with new lighting where the kids will sit and eat.

In addition, doors throughout the district with knobs are being replaced with levers that are American Disabilities Act-compliant.
Phase II, taking more than twice that of Phase I from bond funds at over $11 million, will mostly go to reconstructing sidewalks and roads at the high school and Norwood. The project is also expected to add a batting cage to the high school’s upper gym, renovate the JFK Middle School auditorium, replace Terryville’s roof and replace waterless urinals and sinks throughout the district.
Additional information and pictures about phases I and II of the bond projects can be found at www.comsewogue.k12.ny.us/school_board/bond_status_updates_summer_2019.