PJV Awards Barnum Lot Bid, Secures Grant Funds

PJV Awards Barnum Lot Bid, Secures Grant Funds

by -
0 1928
The site of the planned parking lot on Barnum Avenue. File photo by Kyle Barr

The Village of Port Jefferson finally has an amount attached to plans for the Barnum Avenue parking lot, coming in lower than had been initially anticipated.

The winning bid for the Barnum parking lot was approved at the Feb. 18 village board meeting, showing Connecticut-based F&F Concrete saying it can do the project at $795,069. The company won out over five separate bids. 

At the same meeting, the board approved the $200,000 in jumpstart grant from Suffolk County that was originally announced last year. Unlike other kinds of grants, Mayor Margot Garant said, the jumpstart funds become immediately available after they are approved.

While all the money is now there for the lot, officials said the village is waiting on the grant to finalize, with the village needing to show before shovels go in the ground.

“Ideally, the village would like the project to start as soon as possible so that the lot would be open for our peak season, but that timing has a few factors to consider including but not limited to the weather, execution of the contract, insurance being satisfactory and all county grant requirements being met,” said Joe Palumbo, the village administrator in an email.

With the grant funds, the village administrator said Port Jefferson will be using approximately $600,000 from parking meter revenue. Garant said the parking capital account currently amounts to $800,000. At the end of every year, unspent revenue from the account that’s not used for salaries and other upkeep ends up in the capital account. 

“We have that money in place,” Garant said.

Though village officials had originally anticipated the project would come in at around $900,000, officials were pleasantly surprised to see the winning bid came in somewhat under that amount. 

The parking lot is expected to contain 44 new spots, located off Barnum Avenue and east of the Joe Erland baseball field. Based on residents feedback, the two-way ingress and egress planned on
Caroline Avenue have been made one-way. Surrounding plantings have also been bolstered, but the 32,000-square-foot lot will still include two electric car charging stations and two bioswales bordering the foot entrance onto Barnum Avenue to aid in flood mitigation. Once constructed, the bioswales will look like two dips in the ground with plantings overlaying them. Port Jefferson grant writer Nicole Christian had said those plantings and green initiatives were a large reason the county provided the village the $200,000 grant.