Northport High School has replaced its wood bleachers, pictured above at a prior homecoming celebration. File photo

By Kevin Redding

The Northport-East Northport Tigers’ challenges this football season have given them a whole new perspective on why there’s no place like home.

On Saturday, Oct. 14, Northport-East Northport’s varsity football team will celebrate homecoming by stepping onto their own field for the first time this season after a recent announcement that the district has completed its thorough and long-proposed bleacher repairs.

The process of replacing the football field’s deteriorated wooden bleachers with new metal bleachers officially began in late August and ended Monday, Oct. 9. This was a period of frustration and uncertainty for many parents and players within the district as it forced the Northport Tigers to go to other fields for the first two home games of the 2017 season.

The team’s first home game in September was moved to Elwood-John H. Glenn High School. Their Oct. 1 game was relocated to Half Hollow Hills High School East’s field.

Northport High School. File photo

The new structures passed inspection with Texas-based LandTech Inc. at the helm of construction. Total cost for the project was more than $1 million, which came from the district’s general fund as well as state aid, according to school officials.   

“We’re going to be back on course for homecoming Saturday,” Northport Superintendent Robert Banzer said.

A former football player himself, Banzer claimed the stadium had the same wooden bleachers when he was there in the early 1980s. The upgraded bleachers are far less dangerous and were built in compliance with the Americans with Disabilities Act.

“I’m excited to have everybody see the work but, most importantly, to be at home,” he said. “It’s always a very fun time.”

Banzer and the school board initially approved the bleacher repairs in the 2015-16 budget, along with a variety of infrastructure projects throughout the district. But the construction couldn’t move forward on it right away as it faced a lengthy state approvals process.

The first opportunity the school district could seize to begin repairs was in late spring of this year prior to
graduation ceremonies. Banzer said he didn’t want to risk the job not being done in time for a large event. By the time the district hired LandTech to build the bleachers, the construction company was booked for most of the summer and couldn’t begin the project until a couple weeks into August.

School officials projected the bleachers would be finished by the team’s second home game, but as that proved to be overambitious, the community grew increasingly anxious that the job wouldn’t be done in time for homecoming. Some residents made sure their voices were heard.

“It’s a disgraceful, embarrassing, hurtful situation that in my opinion could’ve been avoided,” Mike Gozelski, president of the Northport Football Booster Club, said during the Sept. 28 board of education meeting. “We’re halfway through the season and the athletes, marching band, cheerleaders and the community have yet to set foot on our home field. It’s heartbreaking for most of us. Part of our anger comes from the fact that work on the bleachers didn’t start until August with football season starting in September. It’s negligent.”

Gozelski, a former Tiger, said for many seniors on the team, including his son, this season is the last chance they had to show their school pride in the stadium.

A previous Northport running back rushes across the football field. File photo by Bill Landon

“These kids practice for two hours a day and work hard 12 months a year to be able to play on this field,” he said. “You have to understand how disappointing this is for them.”

Banzer responded, explaining the school’s side of the situation to Gozelski, as well as about a dozen parents and football players in uniform in the room.

“I know it’s disappointing,” the superintendent said. “But we also wanted to make sure we provided the best product going forward. We just want the job to be done right.”

At the end of the exchange, the board said it was hopeful the bleachers would be ready to go for the district’s pep rally Oct. 13 and Oct. 14 homecoming.

Gozelski said he received the good news from the school’s athletic department on Monday morning.

“Now we’re going to be out there and opening up a brand new, refurbished Tigers stadium,” Gozelski said. “The players get to play, the band gets to play, the cheerleaders get to cheer and the community gets to see a good football game … and hopefully a victory.”

Gina Macchia-Gerdvil, a mother of two students on the team and a member of the Booster Club, was equally upset over the situation, believing the district should have replaced the bleachers after the football
season was over. She said up until Monday’s announcement, nobody was certain if homecoming would take place at home.

“I’m excited for all the kids,” Macchia-Gerdvil said. “My boys are in their second year on varsity and they haven’t had a chance yet to step into their stadium and see the big crowd and all the festivities.”